Tuesday, October 25, 2016

10/26/2016 Blog #8

Hi,
this week I drew the design that I sent to Kearny Foundry and requested a quote. I was trying to do Finite Element Analysis (FEA) on the track but it would not work since the entire loop was created as an assembly and our SolidWorks did not support that so I simply redrew the loop as one part to get an FEA for it. I also worked on the PowerPoint for Presentation #2 and created a spreadsheet to tabulate our inventory and things we might need. Afterward, I searched for several sites that would sell ALU 6061 and found that Eric's recommended company, Coast Aluminum, was the cheapest.


                                           

Tuesday, October 18, 2016

10/19/2016 Blog #7

Hi,
This week, I helped draft a bracket mount that would be specific to the curved track, but soon realized that the radius was so much larger that the curve on the bracket mount would be meaningless and costly. The picture below demonstrates the radius of the loop on the track and the mount with specific legs would align perfectly with the bend to reduce wiggle. However, as can be seen in the picture, the radius is so large that the tangential point of contact is negligible. It would take money to put in that extra radius that effectively accomplishes little. Next, I was also helping Jez change the units of the entire track from metric to standard since we wanted to make the numbers look good with a perfect three significant digit number. However, the dimensions of the track would change and we would have to build a new track, so we agreed to just change the units and leave as is for now until we begin working on the new track next semester. I also compiled a list of things that we will be addressing tomorrow before the presentation on the 26th of October, including, but not limited to, drafting a bill of materials, documenting inventory, contacting companies like Vander-Bend Manufacturing, performing FEA on our assembly, updating Gantt Chart, and creating a PowerPoint.



Franklin Kha


Tuesday, October 11, 2016

10/12/2016 Blog #6

Hi,
after we completed our presentations, I went ahead and posted our slides on the team blog as instructed. There were only a few minutes remaining of class time when the presentations were over and so we all dispersed. This was a fairly mellow week for us, but as according to plan, our goal is to begin calculations and other tests tomorrow on the designs we have. The plan is to finish by the 19th of October. Also, I will continue to update the Gantt chart as needed and the team is currently waiting for some replies about dimensions from the other teams.

Franklin Kha

Tuesday, October 4, 2016

10/5/2016 Blog #5

Hi,
this week I caught the cold so meeting deadlines for my classes and studying for my midterms were already devastating. Aside from the sickness, I worked on the presentation and improved the Gantt Chart because apparently what we were supposed to learn from the videos of Assertion slides, were not simply having fewer words and more blatant pictures - we were supposed to have our titles relay a message. I also updated the PowerPoint so that it would properly and accurately represent what we have done so far, for better or worse. Some individual goals I have for the coming weeks include ensuring we finish the designs and calculations by October 19th and when we later finish the manufacturing, we make sure it remains compatible with the other groups' needs.